An innovative
construction material
from Austria
A total of 132 boards were required for this project and their production took two days. Following the assembly sequence, the KLH boards were duly loaded into the containers which allowed for trouble-free processing on location.
90 days later, the boards arrived at the port of Imari in Saga Prefecture while the foundation building process on site continued according to plan. Thus, no time was lost. In fact, the construction period could be further shortened thanks to the use of KLH solid timber boards.
Project Info
155 cubic metres of KLH solid timber boards which had been transported to the site in four 40 foot containers were used for the construction of Hayama’s Studio.
Architecture
Yukiharu Takematsu & E.P.A
www.epa-arch.com
Wood Construction
Kamiyama Kensetsu Co. Ltd.
Photographer
Naoya Hatakeyama
Location
Takeo-shi, Saga, Japan
Photo Gallery
More References